You may not need to replace all of the windows at your old house. Install weatherstripping to seal the gaps and watch your heating and cooling bills shrink.

TOH Host Kevin O'Connor shows you how to draftproof old-house windows
TOH Host Kevin O'Connor shows you how to draftproof old-house windows


When Kevin O'Connor, the host of This Old House, renovated his 1894 Queen Anne, he never once considered replacing its original double-hung windows with modern ones.

"It would kill me to put new windows in this house," he says. For one thing, the handcrafted sash and blown-glass panes would be costly to replace-as much as $1,000 apiece-and substituting anything less would destroy much of the old place's charm.

Still, he was dismayed by how much air leaked in during the winter, even with outside storm windows in place.

To fix the problem, he needed a product that was both effective and unobtrusive. "I didn't want anything that would change the way the old windows look," he says. The solution: a simple weatherstripping kit that uses the same types of seal found in modern windows and is practically invisible.

For about $60 and an hour's installation time per window, Kevin got the leak-free performance of a new unit while saving a valuable piece of his house's history, as well as dollars off his heating bill. "The wind is blowing outside," he says, "but the drafts are gone." On the following pages, he shows how he did it.

RELATED: 10 Easy DIY Ways to Shrink Your Energy Bills

Get Started: Remove the Sash

Step 1
Step 1

1. Pry off one inside stop.
With a utility knife, break the paint film (if any) by scoring along the joints where the stop meets the side casing and the sill. Remove any screws holding the stop to the jamb. Insert a stiff putty knife in the joint about halfway up the window opening. Gently bend the stop and insert a pry bar in the gap above the knife. Work the two tools down toward the sill, putty knife in the lead, until the stop is free. Pull any finish nails out through the back of the stop, then set it aside.

2. Take out the lower sash.
Raise the sash slightly and swing it out on the side where the stop was removed. Pull the cord out of its groove and tie a figure-eight knot in one end to keep the cord from being pulled down into the weight pocket. If the sash has chains instead of cords, insert a nail through a link instead.

RELATED: Slash Your Energy Bills With a DIY Energy Audit. Here's How to Do It

3. Pull the parting beads.
Using a utility knife, score the paint (if any) on both sides of all three parting beads. Grab each parting bead on one end with nippers or locking pliers and pull it out of its dado, the flat-bottomed groove in the jamb. Move the upper sash as needed to get a good grip. If the upper sash is inoperable, pry out the beads with a chisel, taking care not to gouge the sash. There's no need to remove the upper sash. Its weatherstripping is on the replacement parting beads you'll install later.

Weatherstrip the Sash

4. Rout the meeting rail.
Place the sash on a padded worktable with the exterior side facing up. Clamp the sash so its meeting rail projects a few inches past the edge of the table. Remove the sash lock and set aside. Chuck the slot-cutting bit into the router and set it to cut 3/8 inch from the router base. (A bearing controls the bit's cutting depth.) Hold the router base firmly against the top edge of the meeting rail and cut a groove from left to right.

5. Rout the bottom rail.
Unclamp the sash, rotate it so its bottom rail is closest to you and overhanging the table, then reclamp. Hold the router's base firmly against the face of the rail and cut a groove from left to right.

6. Weatherstrip.
Press the silicone weatherstripping, barbed edge first, into the groove routed into the bottom rail (below). Take care not to stretch the strip as you insert it. Insert the pile weatherstripping into the meeting-rail groove. Use a utility knife to trim the ends of each piece of weatherstripping flush with the outside edges of the sash.

Install the New Beads

7. Replace the top bead.
Lower the upper sash and measure the length of the dado in the head jamb. Mark that measurement on the shortest parting bead in the kit (above left). Cut it to length. Tap the bead into its dado with the pile weatherstripping facing out.

8. Cut the side beads.
Mark the jamb where it meets the horizontal centerline of the sash's meeting rail (above right). Measure up from that mark to the top bead and down from the mark to the sill. Transfer those measurements to the replacement bead, starting from the bead's center; where the weatherstripping on one side ends and the stripping on the other side starts. (The strips on the upper part of the bead should face out.) Trim the top end of the bead square; trim the bottom end to match the angle of the sill. Repeat for the bead on the opposite jamb.

9. Tap in the side beads.
The fit should be tight enough to hold them in place. If it isn't, drill, then tack the bead in place with a few ¾-inch wire brads. Reinstall the sash, stops, and sash lock. When you're done, the sash should slide up and down smoothly and line up at their meeting rails.